Observer Name | Tom Peterson |
---|---|
Date of Inspection | 11/20/2019 |
Site | Field (Wells) |
Area / Job | Rochester / 7096 |
House Keeping | 4 |
Rigging | 3 |
Comments (Rigging) | Top Burke insert was missed by production. Ryan checked capacity of remaining burkes against the panel weight and said it was good to lift. |
Machines and tools | 4 |
Falls Hazards | 4 |
PPE & Signage | 4 |
Electrical | 3 |
Comments (Electrical) | Overhead power line is close to our crane work. The air was very damp so we had to ground to the outrigger to avoid shocks. We also set up delineating posts with ribbon to mark the area. |
Hot Work | 4 |
Heavy Equipment Operation | 4 |
Ergonomics/ Lifting/ Carrying/ Repetitive | 4 |
Inspection Total | 34 |