Colorado Center

Tower III

Denver, CO

Colorado Center Tower 3 is a podium-style office tower with ground level retail, a 6 level garage for 400 cars, and 203,000 ft2 of offices on 8 floors, topped by a roof terrace. Part of a 13-acre, mixed-use Transit Oriented Development (TOD), the new building is designed for LEED Gold certification.

During design, precast concrete construction was selected over structural steel due to its delivery time and cost advantages. According to Scott Halpin of Tryba Architects, the precaster was During design, precast concrete construction was selected over structural steel due to its delivery time and cost advantages. According to Scott Halpin of Tryba Architects, the precaster was brought in as a prime consultant early on in the agreement. Precast, the architect says, “saved us six months and the precast structural system came in at a lower cost than the structural steel.”

The total precast structure includes precast columns, double tees, inverted tees, beams and spandrels. Exterior walls are spandrels with curtainwall glass. Precast was even incorporated into the building architecture by leaving the underside of the double tees exposed in the offices. In addition, mullions for the glazing system were all designed to align with the double tees.

Despite the addition of a roof terrace half way through precast erection, the project is scheduled to come in on time. Taker a closer look at this project with this drone video.

Precast Solution

The number of precast componeents utilized for the project included: 155 spandrels, 170 window walls, 928 double tees, 168 columns, 223 inverted tees, 29 L-beams, and 97 R-beams. The spandrels are buff colored, in acid etched and form liner finishes.

In the office levels, L-beams support the double tees. Adjacent to these are “wallumns.” These are built-up precast wall column sections where exterior window wall panels are cast with large pilasters on the back to reduce the number of pieces. The pilasters helped carry the gravity load to the foundations.

Punched window wall panels were pre-glazed in the precaster’s plant prior to shipping and erection. Glazing had to be protected for weld slag during the erection process. So, a protection system was developed using aluminum frames and light weight fire blankets that were installed over the windows at the jobsite prior to setting.

In the garage levels, load-bearing precast spandrels support the double tees along two facades. Non-load-bearing spandrels cover the other sides. The double tees span 45 feet and are field-topped.

Key Project Attributes

  • Project converted from steel to precast
  • Total precast structure: columns, double tees, inverted tees and spandrels
  • Exterior walls are spandrels with curtainwall glass
  • Use of precast cuts six months off project delivery time
  • Podium designed garage and office tower
  • Part of a 13-acre, mixed-use Transit Oriented Development (TOD)
  • Designed for LEED Gold certification
  • Locally produced, precast offers little waste, 12.2% fly ash in the mix
  • Underside of the double tee exposed in the office
  • Glazing mullions designed to align with the double tees

Project and Precast Scope

  • Punched precast window wall panels pre-glazed in the plant
  • Built-up precast “wallumns” — wall panels cast with pilasters on the back
  • Ground floor retail
  • 6 level garage for 400 cars
  • 8 level, 203,000 ft2 office tower
  • 168 precast columns; 29 precast L-beams; 97 precast R-beams
  • 155 buff colored precast spandrels in acid etched and form liner finishes
  • 170 precast window walls
  • 928 precast double tees
  • 223 precast inverted tees

PROJECT DETAILS

PRECAST PRODUCTS